Refreshed at : 3:06:19 AM
Monday Tuesday Wednesday Thursday Friday
1 - Mar
2 - Mar
3 - Mar
4 - Mar
5 - Mar
8 - Mar
9 - Mar
10 - Mar
11 - Mar
INT
3/9 08:50
EXT
3/9 08:50
FRAME
3/10 07:08
TRIM
3/10 07:07
12 - Mar
INT
3/10 08:38
EXT
3/10 08:38
FRAME
TRIM
3/9 12:41
15 - Mar
INT
EXT
FRAME
TRIM
16 - Mar
INT
EXT
FRAME
TRIM
17 - Mar
INT
EXT
FRAME
TRIM
18 - Mar
INT
EXT
FRAME
TRIM
19 - Mar
INT
EXT
FRAME
TRIM
22 - Mar
INT
EXT
FRAME
TRIM
23 - Mar
INT
EXT
FRAME
TRIM
24 - Mar
INT
EXT
FRAME
TRIM
25 - Mar
INT
EXT
FRAME
TRIM
26 - Mar
INT
EXT
FRAME
TRIM
29 - Mar
INT
EXT
FRAME
TRIM
30 - Mar
INT
EXT
FRAME
TRIM
31 - Mar
INT
EXT
FRAME
TRIM
1 - Apr
INT
EXT
FRAME
TRIM
2 - Apr
INT
EXT
FRAME
TRIM

HOME

INT = Interior Door Shop Production (If this is "red", the schedule is full and no doors can be assembled)
EXT = Exterior Door Shop Production (If this is "red", the schedule is full and no doors can be assembled)
FRAME = Frame Material Delivery (Yellow = AM runs are full, Red = all framing material deliveries are full)
TRIM = Frame Material Delivery (Yellow = AM runs are full, Red = all framing material deliveries are full)